













|
 |
SLUDGE STABILIZATION CASE HISTORIES |
|
NORTH AREA CLOSURE Nederland, Texas
This project included closure of 4 hazardous waste impoundments totaling approximately 80 acres. The project involved placement of over 300,000 cubic yards of imported soils, 1.5 million square feet of geosynthetic clay liner (GCL), 1.0 million square feet of geogrid, and stabilization of over 65,000 cubic yards of excessively soft sediment. Work also included installation of a vinyl sheet pile wall to control the migration of NAPL-impacted groundwater off-site.
The project began in July 2004, with a milestone completion date of September 15, 2005. Even with weather related delays, RECON was able to complete the work by July 2005, two months ahead of schedule.
There are several reasons that attribute to us completing this work on time and under budget.
- RECON utilized an excavator mounted on swamp pontoon tracks to install several drainage ditches in excessively soft sediment/ sludge. This coupled with simple sump dewatering techniques proved to lower the water elevation in the sludge, forming a two-foot thick crust. This allowed low-ground pressure dozers to traverse most of the area. Other very soft areas within the impoundment were stabilized using fly ash, a by-product generated from a local power plant. Long-stick excavators were used to mix the fly ash with the sludge. By excavating drainage ditches, RECON used 50% less fly ash during the project. In addition, we were able to use normal strength bi-axle geogrid in lieu of high-strength.
- Clean sand was to be placed above geogrid for purposes of serving as a pressure-relief layer and GCL bedding layer. Since the drainage ditches were installed, sand was no longer required to serve as a pressure-relief layer. RECON substituted a more readily available sandy clay [60-40] material in place of the sand. RECON crews installed both geogrid and GCL.
- In order to speed-up the construction schedule to receive a minimum of 200 loads of dirt per day, RECON developed and operated a borrow pit and purchased 17 dump trucks. With the help of local hauler, RECON was able to haul in excess of 400 loads per day to UNOCAL.
- Last but not least, our field crews make the difference. Much of our success on this UNOCAL project was directly attributed to their ingenuity and willingness to get the project done in a safe and quality manner, productively.
| This Unocal project was one of the most challenging projects RECON has ever undertaken. It involved stabilization, capping, and groundwater control. As a part of the project, we created 20-acres of wetlands. RECON used stabilized masses and reshaped them to look like natural islands and peninsulas. In addition, we installed a concrete outlet control structure that will convey future storm water from the uplands and wetlands to the Neches River. Perimeter access roads were installed around the completed project, which has become a habitat for a wide variety of waterfowl and wildlife species. |
|
|
RECON does what it takes to get a project completed – including the development of a new borrow area and willingness to purchase construction equipment | |
|
| Back to Top |
|
SURFACE IMPOUNDMENT CLOSURE Edgemoor, Delaware
Closure of four surface impoundment ponds at a Delaware facility involved the neutralization and stabilization of 70,000 cubic yards of ferric chloride sludge. The pH of the waste material was less than two standard units, and in the case of one pond less than 0.5. The primary objective for Remedial Construction Services, L.P., (RECON) was to provide sufficient bearing capacity to support a geosynthetic cover system over the sludge material in the future. A second objective of the remediation program was to further control leaching of the impoundment material to ensure that containment levels were below the maximum levels mandated by the Federal Safe Drinking Water Act (SDWA).
Stabilization Program The unconfined compressive strength (UCS) of the stabilized sludge was required to be 15 to 20 psi, in order to support a cap without deformation. To achieve this, as well as meet the leachate and toxicity requirements, RECON used a reagent composed of 20% hydrated lime, 10% Portland cementm and 10% water. The dry reagent components were pneumatically discharged into dust suppressant devices. Where additional dust control was deemed necessary, lime slurry was used in lieu of hydrated lime and discharged from tanker trucks. The reagent was then mixed with the sludge using a trackhoe.
Testing During the work, samples of the treated material were retrieved and analyzed using the Toxicity Characteristics Leaching Procedure (TCLP) and the Synthetic Precipitation Leaching Procedure (SPLP) established by the EPA to determine contaminant migration levels in groundwater. Results confirmed that the neutralization and stabilization program had met both the RCRA toxicity characteristics requirements and the Federal SDWA acceptable contaminant levels.
In addition to the sludge remediation work, RECON installed a gravity drain system to allow rainwater from three ponds to collect in the fourth pond in preparation for channeling to the facility's water treatment unit. |
| Back to Top |
SITE 15 SOLID WASTE DISPOSAL BASIN CLOSURE Roxana, Illinois
A 20-acre, aboveground retention basin recently used for disposal of lime slurry from the treatment of boiler feed water and cooling water had been formerly used for disposal of API oil separator sludge. When the basin was removed from operation, Remedial Construction Services, L.P. (RECON) was retained to:
-
Stabilize approximately 300,000 cubic yards of sludge, and
-
Design and place an engineered composite drainage cap.
Phase 1: Sludge Stabilization The stabilized reagent was a mix of Class C flyash, cement and bed ash. Prior to the work, RECON performed several test studies to determine the ratio of reagent components that would best meet the performance requirement of an unconfined comnpressive strength of 25 psi at 28 days in accordance with ASTM D2166.
The sludge was solidified in place to an approximate depth of 12 feet using five track-mounted excavators equipped with reagent injectors and special rake attachment sludge mixers which, when used correctly, also control the reagent dust problems inherent to this type of solidification work. Depending on the density and physical characteristics of the encountered sludge, a customized bulk material deployment tent was also used for controlled off-loading of the reagent, which was then carefully placed and mixed with the insitu sludge using a standard excavator bucket. During the solidification process, RECON maintained a zero air or sediment release. Following solidification, the material was excavated and re-graded to form a sub-base in preparation for the Phase 2 construction of the engineered cap.
Phase 2: Drainage Cap Construction Construction of the engineered cap consisted of:
-
Placement of a one foot thick cohesive soil barrier, with a hydraulic conductivity less than or equal to 1x10-5 cm/sec, over the re-graded material.
-
Compaction of the soil barrier to meet a requirement of at least 95% by dry unit weight, as measured by ASTM D698.
-
Installation of a 40-mil polyethylene geomembrane liner.
-
Placement of a non-woven geotextile fabric, a one-foot thick granular drainage layer and a second geotextile fabric.
-
Placement of a six-inch protective soil cover, followed by six inches of topsoil in preparation for seeding. |
| Back to Top |
|